DiMeo Brothers, the contractor for the project, is planning on performing a water main shut down as follows:
Areas Affected: Nora Avenue from Harrison Street to southerly limits of roadway
Day: Tuesday, April 30, 2013
Start Time: 9:00 AM
Duration: 6-8 Hours
All affected residents will receive a door hanger on Monday, April 29th with further information and details.
Thank you in advance for your patience during this process.
Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:
. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica
Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction
. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica
Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction
Friday, April 26, 2013
Work is Starting
The general contractor, Dimeo Bros. Inc., will continue mobilizing next week and will begin construction. Next week contractor will begin water main installation on Nora Avenue.