Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Friday, June 7, 2013

Storm Sewer Continues on Nora, North of Colfax

This past week the contractor completed installing the new storm sewer, storm sewer services, and water services along Nora Avenue south of Colfax Avenue. The contractor began the same process of installing storm sewer mainline, storm sewer services, and water services north of Colfax Avenue along Nora Avenue.
Next week the contractor will continue to work along Nora Avenue, north of Colfax. The same process of installing water services, storm services, and storm main line is anticipated to continue.
During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.