This past week the contractor completed installing the new storm sewer, storm sewer services, and water services along Nora Avenue south of Colfax Avenue. The contractor began the same process of installing storm sewer mainline, storm sewer services, and water services north of Colfax Avenue along Nora Avenue.
Next week the contractor will continue to work along Nora Avenue, north of Colfax. The same process of installing water services, storm services, and storm main line is anticipated to continue.
During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.Thank you for your patience during the construction operations.