Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Friday, April 26, 2013

Work is Starting

The general contractor, Dimeo Bros. Inc., will continue mobilizing next week and will begin construction. Next week contractor will begin water main installation on Nora Avenue.