Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Friday, July 26, 2013

Curb & Gutter Completed. Asphalt Paving Next Week

This past week the contractor performed roadway reconstruction along Nora Avenue and Neva Avenue south of Colfax Avenue. The contractor completed roadway excavation, installation of new aggregate base course, and concrete curb & gutter.
Next week the contractor will complete the concrete driveway and sidewalk replacements, grading behind the new concrete curb & gutter, and fine grading of the aggregate material. Asphalt paving of Nora Avenue and Neva Avenue south of Colfax Avenue is scheduled mid to late next week depending on weather and scheduling conflicts.
The contractor is anticipating to work on Saturday, June 27th, starting at 9:00 AM, to perform landscape grading behind the installed concrete curb & gutter.
The contractor anticipates to begin roadway reconstruction on Nora and Neva Avenue north of Colfax Avenue the week of August 5th.
We ask and thank you for your cooperation in following the directions detailed in previous mailings regarding access to your driveways and homes during the roadway reconstruction process.