Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Monday, July 8, 2013

Storm Sewer Nearing Completion on Neva Avenue

This past week the contractor continued to install storm sewer mainline, storm sewer services, and water services along Neva Avenue north of Colfax Avenue. The contractor also completed installing the internal epoxy liner within the sanitary sewer manholes located in the rear easements.
This week the contractor will likely complete the installation of storm sewer mainline, storm sewer services, and water services along Neva Avenue north of Colfax Avenue. The contractor will then work on the water main connections between the new and existing systems. The underground work should be completed within the next two weeks. Following the underground utility construction, the contractor will begin the roadway reconstruction process.
The connections to the existing water main will require the water to be shut-down for a period of time while the work is being completed. Residents will be notified 24-hours in advance of any scheduled water shut-down.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Thank you for your patience during the construction operations.