Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Friday, October 11, 2013

Asphalt Milling to be Performed this Week

This past week the contractor performed roadway excavation, aggregate base installation, and asphalt binder paving along Colfax Avenue within the Nora Avenue and Neva Avenue intersections. The contractor also performed some miscellaneous repairs and site clean-up. The Village staff also performed a final walk-through of the project to identify any additional repairs that need to be made prior project completion.

Next Tuesday, October 15th, the paving sub-contractor is scheduled to mill the existing pavement surface along Colfax Avenue from Waukegan Road to Harlem Avenue. The landscaping sub-contractor is also anticipated to be in next week to perform the remaining sod restorations along Colfax Avenue.
The asphalt surface paving along all roadways is scheduled to be performed the week of October 21st.

During milling and paving operations, we ask for your cooperation in not parking on the street and minimizing the amount of travel in the area.
We continue to express our gratitude during the on-going construction. The completion of the asphalt surface paving in the next few weeks will mark a significant milestone in the overall completion of the project.