Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Friday, October 25, 2013

Project Complete

This past week the pavement marking sub-contractor performed the pavement markings along Colfax Avenue. DiMeo Brothers have also been on-site completing some of the minor repairs indicated on the punch list.  

Next week, the landscape sub-contractor is scheduled to be on-site to complete the landscape restorations along Colfax Avenue.  The general contractor is anticipating all punch list items will be completed next week.
The major construction items along the entire project site are completed with only a few minor items remaining. This will be the last blog post for this project. We hope you enjoyed reading the blogs and found the information useful and informative.

We would like to express our gratitude one last time for all of your patience dealing with the inconveniences of construction along your streets and within your neighborhood.
In the next few weeks, a survey regarding the construction project will be mailed to you. We would appreciate a few minutes of your time to complete and return the survey. The surveys are very helpful in determining what aspects went well and what portions of construction process we need to improve.

If you have any further questions or concerns, please contact Scott Huebner, Village Project Manager, at 847-904-4420.