Project scope consists of roadway, curb and gutter replacement sidewalk repairs, new storm sewer, new water main and parkway restoration. The project improvements include:

. New curb and gutter
· All new asphalt pavement
· Storm sewer replacement and upsizing with new homeowner sewer services
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
· Sidewalk repairs
. Paving of Colfax from Harlem to Nordica

Project Timeline April 2013 – Start of Construction
November 2013 – End of Construction

Monday, October 7, 2013

Traffic Calming Islands Installed

This past week the contractor installed the concrete traffic calming medians and sidewalk ramps at the intersections of Nora Avenue and Nottingham Avenue.

Next week, the contractor is anticipated to complete the roadway excavation and asphalt binder layer at the intersections of Colfax Avenue at Nora Avenue and Neva Avenue.
Following the asphalt binder at Nora Avenue and Neva Avenue, the contractor will mill the existing asphalt surface along Colfax Avenue from Waukegan Road to Harlem Road. The final asphalt surface layer along Colfax Avenue, Nora Avenue, and Neva Avenue will be installed at the same time once all other work is completed.

We appreciate all of your patience as the construction process continues.