This past week the contractor installed new storm sewer starting on Nora Avenue at Colfax Avenue and working south to the end of the street. As the contractor installed the main line storm sewer, they are also installing new storm sewer services and water services to individual homes.
Next week the contractor will continue to install storm sewer along Nora Avenue, south of Colfax. The contractor is anticipating to continue to install storm and water services as the storm sewer is being installed.
During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.Thank you for your patience during the construction operations.